As a way to keep you informed on the progress of Villago, we will continue to update you at various times throughout the construction process. You'll find it's a great way to get the latest news on Casa Grande's BEAUTIFUL master-planned community.
INFRASTRUCTURE
The replacement and removal of curbs, gutters and sidewalk along the infrastructure is virtually complete, and the city is expected to accept the main and arterial streets at Villago in the very near future.
The streetlights along the infrastructure are 95% complete with only minor adjustments remaining. In fact, streetlights are now illuminated throughout the infrastructure from dusk until dawn. Currently, APS is focusing its efforts on completing electrical installations within the parcels, and working on the infrastructure’s electrical system at a slower pace.
Landscaping along both the infrastructure and Pinal Avenue continued this month. Decomposed granite, trees, bushes, extruded curb, and shrubs were all installed. Plant and shrub installation is an ongoing project, with more than 2,000 shrubs arriving on-site this month. Palm trees continue to arrive, and some have been installed behind the monuments and throughout the infrastructure, adding an aesthetically pleasing vertical aspect to the project. The lighting for the palms will be installed at the end of October.
Project contractor AAA recently completed grading of Villago’s regional park, and irrigation specialists are now working to get this future green space growing.
ONSITE
As Villago continues to satisfy regulations for its parcels, the project has begun to receive approvals for permanent certificates of occupancy, allowing the community to continue its fast-paced development.
The perimeter wall is 95% complete, with only minor final adjustments still being made. Concrete, paving and the installation of electrical equipment are now officially complete within the parcels. Ramadas and tot lots also continue to be installed, along with other landscaping features.
The common area sidewalks are 95% complete, and paver bands are scheduled to be installed soon. The final walk-through for the electric has occurred and the electrical installation is 90% complete, leaving only meters to be installed and a few minor adjustments to be made.
OFFSITE
The barricades have been removed and the main entrance to Villago – Villago Parkway – is now open and accessible from Pinal Avenue. Construction continues to move forward at the Pinal Avenue entrances, and Ocean View Drive is under construction with storm drain currently being installed.
|